Changing a plan

  figure44
Figure 5:   Change the decomposition of a task

When the reasons for a decomposition becomes invalid or the planner has changed his mind about it, any decomposition can be undone, old decompositions can be redone. Figure 5 shows a dialog that allows to replace a current decomposition with an old one. Decompositions are modeled as decisions in Redux, but the Applet tries to hide that fact from the planner.